Software Development Life Cycle
28 Aug 2012

This is the SDLC checklist that we used in the early days of Fareoffice. It can be seen as all steps used in a 14-28 days sprint. In some way I think it’s still very valid.

M = Manager/Product owner. U = User of the product. R = Reviewer D = Developer

  • 2-8h - Stories/Requiremnts (MURD)
  • 2-4d - User documentation (Think Document Driven Development) / Requirement documentation. (D)
  • 2h - Review (RD)
  • 2h - Acceptance (MURD)
  • 2-4d - Architecture/Detail design/Tasks/Issues (D)
  • 2h - Review (RD)
  • 2h - Acceptance (MRD)
  • 10-25d - Implementation (D)
  • 1-2d - Testing (RD)
  • 2-8h - Acceptance test (MURD)